Two stations of Metro Line No.1 expected to complete before April 30

The HCMC Urban Railway Management Unit has made every possible effort to finish two stations of the Ben Thanh-Suoi Tien Metro Line No 1 , including Binh Thai and Hi-tech Park before the National Reunification Day, April 30.
Binh Thai station under construction
Binh Thai station under construction
Every station has two storeys and a length of 137 meters connecting with pedestrian overpass over the Hanoi highway.
The line No. 1 consists of 11 stations, including Van Thanh, Thao Dien, Rach Chiec, Phuoc Long, Binh Thai, Thu Duc, High-tech Park, Suoi Tien, Tan Cang, An Phu ...
Metro Line No. 1 runs abut 20 km from Ben Thanh to Suoi Tien, passing through Districts 1, 2, 9, Binh Thanh, and Thu Duc in Ho Chi Minh City and Di An district in Binh Duong.
The line is expected to open in 2020, including 2.6 km of underground line with three stations and over 17 km of elevated line with eleven stations with total capital of US$2.49 billion.